Home |
Search |
Today's Posts |
#1
posted to rec.boats.cruising
|
|||
|
|||
Block Island RI - OLD Harbor
If they get there way no more rafting in Old Harbor.
Harbormaster presents ambitious management plan for Old Harbor By Peter Voskamp Old Harbor's outer basin filled with dozens of rafted yachts last July 4 weekend. Harbormaster Chris Willi has proposed a plan to remedy overcrowding and provide better emergency access for the entire Old Harbor. Photo by Emily Lindquist Harbormaster Chris Willi impressed the Harbors Committee with a PowerPoint presentation on Tuesday night, Jan. 17, detailing a conceptual plan to rearrange and manage Old Harbor. It included not only a much-discussed infrastructure rehabilitation of the south and west docks in Old Harbor's inner basin (new bulkheads, utilities, planking and lighting), but also a new two-story office/bathroom/shower facility on the south dock. And, perhaps most ambitiously, the rebuilding of the Mount Hope dock, a 500-foot pier inside the eastern breakwater, as well as another brand new dock within the western breakwater. Willi stressed that though the creation of new dock space was an integral part of the plan, the reason for it was not to bring more boaters to the island, but rather to accommodate fewer boats in a safer manner, spreading them out to allow for better fire and rescue access. Also, more revenue could result for the town. Willi said during a busy summer weekend too many boats anchor haphazardly along the large breakwater and in the outer basin; at times dozens of vessels raft up to one another. The town cannot regulate the number of boats in the outer basin, Willi said, and also has little access to them in the event of an emergency. The inner basin is similarly plagued by excessive rafting in the summer, with rows of vessels tied up side-by-side. The rafted vessels are not only unable to access any utilities such as water and electricity, but also are in a very precarious position in the event of fire or other emergency. Willi went through frame after frame of the presentation, asking the commissioners for any suggestions they might have. The presentation, projected on screen, included historic photographs to illustrate different points. Willi plans to give a similar presentation to the Town Council next week. Police Chief Vin Carlone was on hand and supported the changes "100 percent." Although the new arrangement might create more work for the police force, Carlone said it would prove a vastly more responsible arrangement than what is currently in place. And, as Willi has previously said, the entire project could be financed with an approximately $3-million bond, which the Harbors Department would shoulder from its own revenue with no expense to taxpayers. The inner basin Apart from the two-story bathroom/ shower facility and extensive rehabilitation of the infrastructure, Willi envisioned decking over areas along the west dock that are open and without planking currently. Also, he suggested moving the bait dock to the end of the inner basin breakwater on the west side. Vice Chair Hermann "Bo" Gempp said a roof over the bait dock would be a good idea, and Gary Hall, a commercial fisherman, said that the small stone jetty out to the current bait dock would need some attention because stones are coming loose; and perhaps planking could be extended to connect to it as well. Willi showed a proposed stern-to docking arrangement in the inner basin. He said it would be safer, and more boats could be accommodated than with a recently proposed two-boat rafting limit for the inner basin. Once the changes are in place, the town could charge the industry standard $4-per-foot dockage fee, instead of the $2.50 it currently does. Also, the electricity could be metered. There was some discussion if a flat rate should be charged for power, or if metering would be the best route. The outer basin and western breakwater Willi's plan showed a dock wrapped within the western breakwater interior, stretching 800 feet, and 8 feet wide. It would accommodate 40 to 45 slips, and would require approximately 20,000 cubic yards of dredging. It would also tie into a boardwalk, which has been proposed in the Old Harbor Vision study, and another small Harbors Department building would be placed there. If this dock were installed, no more anchoring would be allowed in Old Harbor's outer basin, though some moorings would be available. Mount Hope dock The plan showed a rebuilt Mount Hope dock (the original was destroyed in the 1938 Hurricane). At 500 feet long and 8 feet wide, it would provide approximately 20 to 25 slips. Ten thousand cubic yards of sand would have to be dredged to accommodate the dock. Costs Willi provided a breakdown of cost estimates. The numbers came from a Narragansett-based marine construction firm that was here in the fall to work on the new eight-slip marina for Ballard's Wharf. Willi said the numbers are for current material costs, and could rise by 15 percent in just the next six months. The inner basin south dock construction cost was estimated to be $896,000 (the two-story building not included); the west dock: $201,000; the Mount Hope dock: $610,000; the west breakwater site: $1,595,000. The total comes to $3,302,000 - not far off from Gempp's original bond estimate a few months ago. Willi then provided a detailed breakdown of the potential revenue the expanded dock areas could bring in. Based on a 90-day season at 50-percent capacity, the changes could bring in $607,200; at 75-percent capacity: $897,000; and at 100-percent capacity, $1,212,000. Gempp said there would be revenue coming in from Great Salt Pond that was not included in the figures. Though he is still awaiting concrete bond service costs from town Finance Director Tom Moon, Willi outlined the attendant expenses he expects to come with the new infrastructure (garbage, electricity, water, more employees, and debt service for example), which would amount to about $560,000 annually. Willi also said that if any or all of the suggestions were adopted by the town, he'd recommend the work not be done in a piecemeal fashion, otherwise it would not pay for itself. Committee member Renwick "Pete" Tweedy said that when talking to the Town Council, it must be stressed that "doing nothing is not an option," given the deteriorated condition of much of the Old Harbor inner basin. The group applauded Willi's efforts and offered encouragement. Willi asked for "devil's advocates," so the presentation can be made as seamless as possible. He also would like to give the presentation to the Block Island Residents Association, the Block Island Maritime Institute and the Fire Department and Rescue Squad. After the meeting, Willi said that Old Harbor is designated a Type 5 body of water, which is primarily for commercial interests, as opposed to New Harbor, which is Type 3 for mixed use. Officer re-elections, boat salvage The leadership of the Harbors Committee was re-elected Tuesday night, with William Luddy remaining chair, and Gempp remaining vice chair. Willi said that tentative plans are underway to remove the 80-foot Aggressor , a trawler that has been up on the rocks near Black Rock since Thanksgiving. He said the Coast Guard is satisfied there is no more fuel on board the boat, and a salvage barge will arrive on Jan. 23 or 24 to lift the boat and take it away. In February, the Harbors Department will refloat the much smaller Martin boat still on its side off Mosquito Beach, using a recently acquired patrol boat, if the owner does not do so on his own. New regulations allow the department to fine the owner for this effort, and for not addressing the issue sooner. |
Thread Tools | Search this Thread |
Display Modes | |
|
|
Similar Threads | ||||
Thread | Forum | |||
Huntington Harbor | General | |||
where to get a 351 HO long block | Cruising | |||
Links to info about the role of the USCG at Pearl Harbor | General | |||
Cracked block from overheating - help | General | |||
Cracked block from overheating - help | General |